“This has been a very active period for the American Centrifuge project
as we prepare the initial cascade of AC100 series machines for
closed-loop operations in the third quarter and continue to value
engineer the centrifuge design in preparation for high-volume machine
manufacturing next year,” said
“We have also been in active discussions with the
American Centrifuge Overview
We have been developing and demonstrating a highly efficient uranium
enrichment gas centrifuge technology that we call the American
Centrifuge. We are deploying this technology in the American Centrifuge
Plant being built in
We refer to our production centrifuge machine design as the AC100 series
centrifuge machine. The AC100 series machine is designed to produce 350
SWU per year, which output is substantially greater than our
competitors’ machines. Within this overall AC100 design, we have
finalized two design releases. The first was released to our strategic
suppliers in 2008 in preparation for installing a test cascade of these
AC100 series machines in
The American Centrifuge uranium enrichment technology has demonstrated performance above our current target of 350 SWU per machine, per year. Our plan is to seek sustained improvement in centrifuge design that will be integrated into the commercial plant over time. Before a new version of the machine is introduced into the ACP, a design review board will determine through a disciplined process if the improvements provide sufficient cost and performance improvement to implement.
At our state-of-the-art test facilities in
Project Funding
We are seeking an expeditious funding commitment by DOE and financial
closing later this year. However,
Initial AC100 Series Cascade
Our strategic suppliers have been manufacturing parts for the initial
AC100 machines since 2008. In manufacturing parts for the AC100,
suppliers must replicate on a commercial basis manufacturing that we
previously self-performed in building our prototype machines. We are
working with leading companies to create a world-class industrial
infrastructure needed to build components for the AC100 machines and
supporting equipment. The specialized U.S. manufacturing base needed to
build the AC100 did not exist but is being established with our
leadership. Under contract arrangements with
A cascade of initial AC100 machines is expected to be operational early in the third quarter of 2009. This cascade will be in a closed-loop configuration as required under our demonstration license from the NRC but will otherwise operate under commercial plant conditions. During this continuation of our Lead Cascade testing program, we expect to obtain data on machine-to-machine interactions, plant design, subsystem performance, various support systems such as the service module, and cascade electronic control systems. Many of the initial machines for this cascade have been assembled, are operating and are being conditioned with uranium hexafluoride gas in preparation for cascade operations. Additional machines will be added during the summer until we reach 40 to 50 AC100 machines in Lead Cascade testing. These 40 to 50 machines are expected to operate into 2010.
We expect the first machines in the initial AC100 series cascade will have a throughput somewhat less than 350 SWU per year as we continue to optimize the AC100 series machine. However, we remain confident that the AC100 series machines that are deployed in the commercial plant will achieve an average performance level of 350 SWU per year, supporting an annual SWU production capacity of the ACP of 3.8 million SWU.
ACP Work Continues
During the first quarter of 2009, we announced that we began taking steps to conserve cash and reduce the planned escalation of project construction and machine manufacturing activities until we gain greater certainty on potential funding for the project through the DOE Loan Guarantee Program. However, we continue to invest as planned in engineering design, machine value engineering and the initial AC100 series cascade deployment.
The reduction in the planned escalation principally affected
construction of the plant’s interior infrastructure that had been
expected to ramp up significantly in 2009. Construction of the ACP
includes various systems including electric, telecommunications,
cooling, and water distribution. Although plant construction has slowed
to conserve cash, we have continued with engineering and design for the
commercial plant by
Our decision to slow spending until a decision is made by the DOE Loan Guarantee Program will increase costs and extend the schedule for the completion of the project. We are currently engaged with our strategic suppliers in assessing the potential impact on cost and schedule and the potential impact will depend on the length and severity of our spending slowdown. We expect to provide an update as we gain greater certainty on potential funding through the DOE Loan Guarantee Program.
Customers Contract for ACP Output
Our Marketing and Sales department continues to meet with customers to
sell ACP output, which is important to our financing efforts for ACP.
Sales contracts for this initial output represent a strategic commitment
by customers to ensure a reliable, U.S.-based source of nuclear fuel
that will be available for decades to come. Leading nuclear utilities in
Forward Looking Statements
This news release contains “forward-looking statements” – that is,
statements related to future events. In this context, forward-looking
statements may address our expected future business and financial
performance, and often contain words such as “expects,” “anticipates,”
“intends,” “plans,” “believes,” “will” and other words of similar
meaning. Forward-looking statements by their nature address matters that
are, to different degrees, uncertain. For
Source:
USEC Inc.
Investors: Steven Wingfield (301) 564-3354
Media:
Elizabeth Stuckle (301) 564-3399